Important: Northbound I-95 Exit Ramp to NW 2 Ave is Now at Exit 12B

Week of September 4, 2025

🚧 Starting tonight: continuous 4-day closure of the northbound I-95 Express Lanes. Here is what to expect:

💠 It will be closed between NW 30 Street and SR 860/NE 183 Street/Miami Gardens Drive from Thursday, September 4 at 10 p.m. until Monday, September 8 at 5 a.m.

💠 Closure includes the entry points on eastbound SR 112/Airport Expressway and the intersection of NW 39 Street and NW 10 Avenue.

💠 Vehicles will be directed to use the general purpose lanes on northbound I-95. Click here for more information about the closure.

🌐 Check out all the project details at www.Go-GGI.com.

👉 Follow our social media page on 𝕏 @GoGGI_FDOT for the latest updates.

Project Closures

Map closure September 04 -2025
  • lane closure icon

    Lane Closure

  • local traffic only icon

    Detour

  • new traffic pattern icon

    New Traffic Pattern

Check Live Map

The following closures are scheduled between Thursday, September 4 and Friday, September 12. These closures will allow crews to perform bridge work, roadway paving, drainage work and temporary concrete barrier wall installation.

I-95

  • Around-the-clock Closure: southbound I-95 Express ramp from GGMTF
    Ongoing until Monday, September 8 at 5 a.m., the southbound I-95 express lane ramp from the Golden Glades Multimodal Transportation Facility (GGMTF) is closed and traffic is directed to use the general purpose lanes at NW 151 Street.
  • Around-the-clock Closure: northbound I-95 Express Lanes
    From Thursday, September 4 at 10 p.m. until Monday, September 8 at 5 a.m., the northbound I-95 Express Lanes between NW 30 Street and SR 860/NE 183 Street/Miami Gardens Drive will be closed. Closure includes the entry points on eastbound SR 112/Airport Expressway and the intersection of NW 39 Street and NW 10 Avenue. It also includes the northbound I-95 express lane ramp to the Golden Glades Multimodal Transportation Facility (GGMTF).
  • Full Closure: northbound I-95 at SR 916/NW 135 Street
    On Saturday, September 6 between 11 p.m. and 8 a.m.* and Thursday, September 11 between 11 p.m. and 5 a.m., all lanes along northbound I-95 will be closed at SR 916/NW 135 Street and traffic will be detoured as follows:
    • Exit at SR 916/NW 135 Street and go north on NW 6 Avenue
    • Turn left onto westbound SR 916/Opa-locka Boulevard
    • Turn right onto northbound SR 7/US 441/NW 7 Avenue
    • Take the ramp to eastbound SR 826 Beaches/NW 167 Street
    • Turn left onto northbound SR 915/NE 6 Avenue
    • Turn right onto eastbound SR 860/NE 183 Street/Miami Gardens Drive
    • Take the ramp onto northbound I-95
  • *If delayed by weather, the alternate date for the Saturday northbound I-95 full closure is from Sunday, September 7 at 11 p.m. until Monday, September 8 at 5 a.m.
  • Closure: northbound and southbound I-95 Express Lanes
    From Monday, September 8 to Friday, September 12 between 11 p.m. and 5 a.m., drivers who want to take the northbound and southbound I-95 Express Lanes between NW 30 Street and SR 860/NE 183 Street/Miami Gardens Drive will be detoured to use the general purpose lanes along I-95.
  • Around-the-clock Ramp Closure: northbound I-95 exit to NW 151 Street
    The exit ramp from northbound I-95 onto NW 151 Street (Exit 11) remains closed through summer 2026. Traffic is directed to use the next exit ramp onto eastbound SR 826/NW 167 Street (Exit 12B) or also the previous exit onto SR 916/NW 135 Street (Exit 10B).

  • Lane Closures: I-95 between NW 135 Street and the Golden Glades Interchange
    • At 9 p.m., one lane in both directions will be closed nightly as needed
    • At 11 p.m., a second lane in both directions will be closed nightly as needed
    • All lanes will reopen at 5 a.m.

Florida’s Turnpike

  • Lane Closures: Florida’s Turnpike between SR 860/NW 183 Street/Miami Gardens Drive and I-95
    • From 9 p.m. to 5 a.m., up to two lanes in both directions will be closed nightly as needed

SR 826/Palmetto Expressway

  • Lane Closures: SR 826/Palmetto Expressway between NW 12 Avenue and NW 7 Avenue Extension
    • At 9 p.m., one lane in both directions will be closed nightly as needed
    • At 11 p.m., a second lane in both directions will be closed nightly as needed
    • All lanes will reopen at 5 a.m.

SR 7/US 441/NW 7 Avenue

  • Ramp Closure: SR 7/US 441/NW 7 Avenue to the Golden Glades Interchange
    On Thursday, September 4 between 10 p.m. and 5 a.m., the ramp from northbound SR 7/US 441/NW 7 Avenue to the Golden Glades Interchange will be closed and traffic will be detoured as follows:
    • Go south on SR 7/US 441/NW 7 Avenue
    • Turn left onto eastbound SR 916/Opa-locka Boulevard
    • Take the ramp onto northbound I-95
  • Ramp Closure: Golden Glades Interchange to SR 7/US 441/NW 7 Avenue
    On Thursday, September 4 and Sunday, September 7 between 10 p.m. and 5 a.m., the ramp from the Golden Glades Interchange to southbound SR 7/US 441/NW 7 Avenue will be closed and traffic will be detoured as follows:
    • Take the ramp to southbound I-95
    • Exit at SR 916/Opa-locka Boulevard and turn right onto westbound SR 916/Opa-locka Boulevard
    • Turn left onto southbound SR 7/US 441/NW 7 Avenue
  • Ramp Closure: northbound SR 7/US 441/NW 7 Avenue to northbound I-95
    On Friday, September 12 between 10 p.m. and 5 a.m., the ramp from northbound SR 7/US 441/NW 7 Avenue to northbound I-95 will be closed and traffic will be detoured as follows:
    • Take the ramp to eastbound SR 826 Beaches/NW 167 Street
    • Turn left onto northbound SR 915/NE 6 Avenue
    • Turn right onto eastbound SR 860/NE 183 Street/Miami Gardens Drive
    • Take the ramp onto northbound I-95
  • Updated Traffic Pattern: SR 7/US 441/NW 7 Avenue between South Biscayne River Drive and Connector Road
    Northbound SR 7/US 441/NW 7 Avenue is reduced from two lanes to one lane, and southbound SR 7/US 441/NW 7 Avenue is reduced from three lanes to two lanes. The exclusive bicycle lane is temporarily unavailable during this work phase.

SR 9

  • Ramp Closure: SR 9 to the Golden Glades Interchange
    On Thursday, September 4 between 10 p.m. and 5 a.m., the ramp from northbound SR 9 to the Golden Glades Interchange will be closed and traffic will be detoured as follows:
    • Go east on SR 916/Opa-locka Boulevard
    • Take the ramp onto northbound I-95
  • Ramp Closure: Golden Glades Interchange to SR 9
    On Thursday, September 4 between 10 p.m. and 5 a.m., the ramp from the Golden Glades Interchange to southbound SR 9 will be closed and traffic will be detoured as follows:
    • Take the ramp to southbound I-95
    • Exit at SR 916/Opa-locka Boulevard and turn right onto westbound SR 916/Opa-locka Boulevard
    • Turn right onto northbound NW 22 Avenue or continue west and turn right onto northbound NW 27 Avenue to access SR 9

NW 167 Street

  • Ramp Closure: NW 167 Street to I-95, SR 9 and SR 7/US 441/NW 7 Avenue
    From Monday, September 8 to Wednesday, September 10 from 10 p.m. to 5 a.m., the ramp from NW 167 Street to southbound I-95, SR 9 and SR 7/US 441/NW 7 Avenue will be closed and traffic will be detoured as follows:
    • Take the ramp to westbound SR 826/Palmetto Expressway
    • Exit at NW 12 Avenue and turn left onto southbound NW 12 Avenue
    • Turn left and take the ramp to eastbound SR 826/Palmetto Expressway
    • Take the ramp to southbound I-95 and SR 7/US 441/NW 7 Avenue
  • Updated Traffic Pattern: NW 167 Street and NW 2 Avenue Intersection
    Northbound NW 2 Avenue is reduced to one exclusive left turn lane. This is a temporary configuration to continue reconstructing the Golden Glades Interchange.

SR 112/Airport Expressway

  • Lane Closures: SR 112/Airport Expressway between NW 22 Avenue and I-95
    • At 10 p.m., one lane in both directions will be closed nightly as needed
    • At 11 p.m., a second lane in both directions will be closed nightly as needed
    • All lanes will reopen at 5 a.m.

NW 171 Terrace

  • Around-the-clock Full Closure: NW 171 Terrace
    NW 171 Terrace between NW 2 Court and NW 2 Avenue remains closed around the clock through summer 2025 for overhead bridge work. Traffic is being detoured to NW 7 Avenue Extension.

NW 6 Avenue

  • Around-the-clock Full Closure: NW 6 Avenue between NW 151 Street and NW 162 Street
    Drivers and pedestrians who want to go north onto NW 6 Avenue from the intersection of NW 151 Street and NW 6 Avenue will be detoured as follows:
    • Go east along NW 151 Street
    • Turn right onto southbound South Biscayne River Drive
    • Take the third exit at the roundabout onto northbound North Miami Avenue
    • Turn left onto northbound Memorial Highway, which converts to NW 2 Avenue
    • Continue north along NW 2 Avenue to NW 165 Street
  • Drivers and pedestrians who want to go south onto NW 6 Avenue from the intersection of NW 165 Street and NW 2 Avenue will be detoured as follows:
    • Continue south along NW 2 Avenue, which converts to Memorial Highway
    • Turn right onto southbound North Miami Avenue
    • Turn right onto northbound South Biscayne River Drive
    • Turn left onto westbound NW 151 Street
    • Continue west along NW 151 Street to NW 6 Avenue

Project Progress

Below is a photograph facing southwest of construction crews installing a concrete wall that will be located next to the future exit ramp from northbound I-95 to NW 167 Street.

Photograph facing southwest of construction crews installing a concrete wall that will be located next to the future exit ramp from northbound I-95 to NW 167 Street (September 2025)