The following closures are scheduled between Tuesday, September 2 and Monday, September 8. These closures will allow crews to perform bridge work, roadway paving, drainage work and temporary concrete barrier wall installation.
Note: lane closures will be suspended from Saturday, August 30 to Monday, September 1 for the Labor Day holiday.
I-95
- Around-the-clock Closure: southbound I-95 Express ramp from GGMTF
Ongoing until Monday, September 8 at 5 a.m., the southbound I-95 express lane ramp from the Golden Glades Multimodal Transportation Facility (GGMTF) is closed and traffic is directed to use the general purpose lanes at NW 151 Street.
- Around-the-clock Closure: northbound I-95 Express lane at the GGI
From Thursday, September 4 at 10 p.m. until Monday, September 8 at 5 a.m., the northbound I-95 Express lane between NW 149 Street and SR 860/NE 183 Street/Miami Gardens Drive will be closed. Traffic will be merged into one express lane when approaching NW 149 Street and directed to use the general purpose lanes along northbound I-95. This closure also includes the northbound I-95 express lane ramp to the Golden Glades Multimodal Transportation Facility (GGMTF).
- Full Closure: northbound I-95 at SR 916/NW 135 Street
On Saturday, September 6 between 10:45 p.m. and 8 a.m. all lanes along northbound I-95 will be closed at SR 916/NW 135 Street and traffic will be detoured as follows:- Exit at SR 916/NW 135 Street and go north on NW 6 Avenue
- Turn left onto westbound SR 916/Opa-locka Boulevard
- Turn right onto northbound SR 7/US 441/NW 7 Avenue
- Take the ramp to eastbound SR 826 Beaches/NW 167 Street
- Turn left onto northbound SR 915/NE 6 Avenue
- Turn right onto eastbound SR 860/NE 183 Street/Miami Gardens Drive
- Take the ramp onto northbound I-95
- Around-the-clock Ramp Closure: northbound I-95 exit to NW 151 Street
The exit ramp from northbound I-95 onto NW 151 Street (Exit 11) remains closed through summer 2026. Traffic is directed to use the next exit ramp onto eastbound SR 826/NW 167 Street (Exit 12B) or also the previous exit onto SR 916/NW 135 Street (Exit 10B).
- Closure: northbound and southbound I-95 Express Lanes
From Tuesday, September 2 to Sunday, September 7 between 11 p.m. and 5 a.m., drivers who want to take the northbound and southbound I-95 Express Lanes between NW 30 Street and SR 860/NE 183 Street/Miami Gardens Drive will be detoured to use the general purpose lanes along I-95.
- Lane Closures: I-95 between NW 135 Street and the Golden Glades Interchange
- At 9 p.m., one lane in both directions will be closed nightly as needed
- At 11 p.m., a second lane in both directions will be closed nightly as needed
- All lanes will reopen at 5 a.m.
Florida’s Turnpike
- Ramp Closure: southbound Florida’s Turnpike to NW 167 Street
On Tuesday, September 2 and Wednesday, September 3 between 11 p.m. and 5 a.m., the ramp from southbound Florida’s Turnpike to NW 167 Street will be closed, and traffic will be detoured as follows:- Take the ramp to southbound SR 7/US 441/NW 7 Avenue
- Make a U-turn at NW 151 Street
- Go north on SR 7/US 441/NW 7 Avenue
- Take the ramp to SR 826 Beaches for NW 167 Street
- Lane Closures: Florida’s Turnpike between SR 860/NW 183 Street/Miami Gardens Drive and I-95
- From 9 p.m. to 5 a.m., up to two lanes in both directions will be closed nightly as needed
SR 826/Palmetto Expressway
- Lane Closures: SR 826/Palmetto Expressway between NW 12 Avenue and NW 7 Avenue Extension
- At 9 p.m., one lane in both directions will be closed nightly as needed
- At 11 p.m., a second lane in both directions will be closed nightly as needed
- All lanes will reopen at 5 a.m.
SR 7/US 441/NW 7 Avenue
- Ramp Closure: SR 7/US 441/NW 7 Avenue to the Golden Glades Interchange
On Thursday, September 4 between 10 p.m. and 5 a.m., the ramp from northbound SR 7/US 441/NW 7 Avenue to the Golden Glades Interchange will be closed and traffic will be detoured as follows:- Go south on SR 7/US 441/NW 7 Avenue
- Turn left onto eastbound SR 916/Opa-locka Boulevard
- Take the ramp onto northbound I-95
- Ramp Closure: Golden Glades Interchange to SR 7/US 441/NW 7 Avenue
On Thursday, September 4 between 10 p.m. and 5 a.m., the ramp from the Golden Glades Interchange to southbound SR 7/US 441/NW 7 Avenue will be closed and traffic will be detoured as follows:- Take the ramp to southbound I-95
- Exit at SR 916/Opa-locka Boulevard and turn right onto westbound SR 916/Opa-locka Boulevard
- Turn left onto southbound SR 7/US 441/NW 7 Avenue
- Updated Traffic Pattern: SR 7/US 441/NW 7 Avenue between South Biscayne River Drive and Connector Road
Northbound SR 7/US 441/NW 7 Avenue is reduced from two lanes to one lane, and southbound SR 7/US 441/NW 7 Avenue is reduced from three lanes to two lanes. The exclusive bicycle lane is temporarily unavailable during this work phase.
SR 9
- Ramp Closure: SR 9 to the Golden Glades Interchange
On Thursday, September 4 between 10 p.m. and 5 a.m., the ramp from northbound SR 9 to the Golden Glades Interchange will be closed and traffic will be detoured as follows:- Go east on SR 916/Opa-locka Boulevard
- Take the ramp onto northbound I-95
- Ramp Closure: Golden Glades Interchange to SR 9
On Thursday, September 4 between 10 p.m. and 5 a.m., the ramp from the Golden Glades Interchange to southbound SR 9 will be closed and traffic will be detoured as follows:- Take the ramp to southbound I-95
- Exit at SR 916/Opa-locka Boulevard and turn right onto westbound SR 916/Opa-locka Boulevard
- Turn right onto northbound NW 22 Avenue or continue west and turn right onto northbound NW 27 Avenue to access SR 9
SR 7/US 441/NW 2 Avenue
- Ramp Closure: southbound SR 7/US 441/NW 2 Avenue to southbound I-95
On Wednesday, September 3 between 10 p.m. and 5 a.m., the ramp from southbound SR 7/US 441/NW 2 Avenue to southbound I-95 will be closed and traffic will be detoured as follows:- Take the ramp to southbound SR 7/US 441/NW 7 Avenue
- Continue south on SR 7/US 441/NW 7 Avenue
- Turn left onto eastbound SR 916/NW 135 Street
- Take the ramp to southbound I-95
NW 167 Street
- Ramp Closure: NW 167 Street to southbound I-95
On Wednesday, September 3 between 10 p.m. and 5 a.m., the ramp from NW 167 Street to southbound I-95 will be closed and traffic will be detoured as follows:- Take the ramp to westbound SR 826/Palmetto Expressway
- Exit at NW 12 Avenue and turn left onto southbound NW 12 Avenue
- Turn left onto eastbound NW 167 Street
- Take the ramp to eastbound SR 826/Palmetto Expressway
- Take the ramp to southbound I-95
- Updated Traffic Pattern: NW 167 Street and NW 2 Avenue Intersection
Northbound NW 2 Avenue is reduced to one exclusive left turn lane. This is a temporary configuration to continue reconstructing the Golden Glades Interchange.
SR 112/Airport Expressway
- Lane Closures: SR 112/Airport Expressway between NW 22 Avenue and I-95
- At 10 p.m., one lane in both directions will be closed nightly as needed
- At 11 p.m., a second lane in both directions will be closed nightly as needed
- All lanes will reopen at 5 a.m.
NW 171 Terrace
- Around-the-clock Full Closure: NW 171 Terrace
NW 171 Terrace between NW 2 Court and NW 2 Avenue remains closed around the clock through summer 2025 for overhead bridge work. Traffic is being detoured to NW 7 Avenue Extension.
NW 6 Avenue
- Around-the-clock Full Closure: NW 6 Avenue between NW 151 Street and NW 162 Street
Drivers and pedestrians who want to go north onto NW 6 Avenue from the intersection of NW 151 Street and NW 6 Avenue will be detoured as follows:- Go east along NW 151 Street
- Turn right onto southbound South Biscayne River Drive
- Take the third exit at the roundabout onto northbound North Miami Avenue
- Turn left onto northbound Memorial Highway, which converts to NW 2 Avenue
- Continue north along NW 2 Avenue to NW 165 Street
- Drivers and pedestrians who want to go south onto NW 6 Avenue from the intersection of NW 165 Street and NW 2 Avenue will be detoured as follows:
- Continue south along NW 2 Avenue, which converts to Memorial Highway
- Turn right onto southbound North Miami Avenue
- Turn right onto northbound South Biscayne River Drive
- Turn left onto westbound NW 151 Street
- Continue west along NW 151 Street to NW 6 Avenue
Project Progress
Below is a photograph facing east of the progress being made on the future direct connect ramp from eastbound SR 826/Palmetto Expressway to northbound I-95. Construction crews are installing the next section of bridge deck side wall for the future ramp.