The following closures are scheduled between Friday, October 4, and Friday, October 11. These closures will allow crews to perform bridge work, roadway paving, I-95 median work, utility work and temporary concrete barrier wall installation.
I-95
- Ramp Closure: NW 151 Street to southbound I-95
From Friday, October 4 at 10 p.m. around the clock until Monday, October 7 at 5 a.m. and Monday, October 7 to Friday, October 11 between 10 p.m. and 5 a.m., the ramp from NW 151 Street to southbound I-95 will be closed and traffic will be detoured as follows:- Continue south on SR 7/US 441/NW 7 Avenue
- Turn left onto eastbound SR 916/NW 135 Street
- Take the ramp onto southbound I-95
- Lane Closures: I-95 between NW 135 Street and the Golden Glades Interchange
- At 9 p.m., one lane in both directions will be closed nightly as needed
- At 11 p.m., a second lane in both directions will be closed nightly as needed
- All lanes will reopen at 5 a.m.
Florida’s Turnpike
- Ramp Closure: southbound Turnpike to westbound SR 826/Palmetto Expressway
From Sunday, October 6 to Tuesday, October 8 from 10 p.m. to 5 a.m., the ramp from southbound Turnpike to westbound SR 826/Palmetto Expressway will be closed and traffic will be detoured as follows:- Continue south and take the ramp to I-95 and SR 7/US 441/NW 7 Avenue
- Exit at SR 7/US 441/NW 7 Avenue and turn right onto northbound SR 7/US 441/NW 7 Avenue
- Take the ramp to the Turnpike and westbound SR 826/Palmetto Expressway
- Continue north and take the ramp to westbound SR 826/Palmetto Expressway
- Lane Closures: Turnpike between SR 860/NW 183 Street/Miami Gardens Drive and I-95
- From 9 p.m. to 5 a.m., up to two lanes in both directions will be closed nightly as needed
- New Traffic Pattern: northbound Turnpike between the Golden Glades Interchange and SR 860/NW 183 Street/Miami Gardens Drive
All three northbound lanes are shifted to the inside using the recently paved shoulder, then shifted to the existing lane configuration when going under the toll gantry and then back to the inside paved shoulder.
Palmetto Expressway
- Ramp Closure: NW 167 Street to westbound SR 826/Palmetto Expressway
From Sunday, October 6 to Thursday, October 10 from 10 p.m. to 5 a.m., the ramp from NW 167 Street to westbound SR 826/Palmetto Expressway will be closed and traffic will be detoured as follows:- Take the ramp to northbound SR 7/US 441/NW 2 Avenue
- Turn left onto westbound NW 7 Avenue Extension
- Continue west for westbound SR 826/Palmetto Expressway
- Lane Closures: Palmetto Expressway between NW 12 Avenue and NW 7 Avenue Extension
- At 9 p.m., one lane in both directions will be closed nightly as needed
- At 11 p.m., a second lane in both directions will be closed nightly as needed
- All lanes will reopen at 5 a.m.
NW 12 Avenue/NW 13 Avenue
- Full Closure: NW 12 Avenue/NW 13 Avenue at SR 826/Palmetto Expressway
From Sunday, October 6 to Friday, October 11 between 9:30 p.m. and 5 a.m., NW 12 Avenue/NW 13 Avenue will be closed in both directions.
- All lanes along northbound NW 12 Avenue/NW 13 Avenue will be closed at SR 826/Palmetto Expressway and traffic will be detoured as follows:
- Turn left onto westbound NW 165 Street
- Turn right onto northbound NW 16 Court
- For eastbound SR 826/Palmetto Expressway or eastbound NW 167 Street, turn right onto the entrance ramp
- For westbound SR 826/Palmetto Expressway, turn left onto westbound NW 167 Street, turn right onto northbound NW 17 Avenue and turn left onto the
- entrance ramp
- For northbound NW 12 Avenue, turn left onto westbound NW 167 Street, turn right onto northbound NW 17 Avenue and turn right onto eastbound NW 175 Street
- All lanes along southbound NW 12 Avenue/NW 13 Avenue will be closed at SR 826/Palmetto Expressway and traffic will be detoured as follows:
- Turn right onto westbound NW 167 Street
- Turn left onto southbound NW 17 Avenue
- For eastbound SR 826/Palmetto Expressway, turn left onto the entrance ramp
- For southbound NW 13 Avenue, turn left onto eastbound NW 167 Street
SR 7/US 441/NW 7 Avenue
- Ramp Closure: Golden Glades Interchange to SR 7/US 441/NW 7 Avenue
From Sunday, October 6 to Friday, October 11 from 10 p.m. to 5 a.m., the ramp from the Golden Glades Interchange to southbound SR 7/US 441/NW 7 Avenue will be closed and traffic will be detoured as follows:- Take the ramp to southbound I-95
- Exit at SR 916/Opa-locka Boulevard and turn right onto westbound SR 916/Opa-locka Boulevard
- Turn left onto southbound SR 7/US 441/NW 7 Avenue
- Ramp Closure: SR 7/US 441/NW 7 Avenue to the Golden Glades Interchange
On Wednesday, October 9 from 10 p.m. to 5 a.m., the ramp from northbound SR 7/US 441/NW 7 Avenue to the Golden Glades Interchange will be closed and traffic will be detoured as follows:- Go south on SR 7/US 441/NW 7 Avenue
- Turn left onto eastbound Opa-locka Boulevard
- Take the ramp onto northbound I-95
- New Traffic Pattern: SR 7/US 441/NW 7 Avenue between South Biscayne River Drive and Connector Road
Northbound SR 7/US 441/NW 7 Avenue is reduced from two lanes to one lane, and southbound SR 7/US 441/NW 7 Avenue is reduced from three lanes to two lanes.
Click here for more information and to download the traffic pattern map.
SR 9
- Ramp Closure: Golden Glades Interchange to SR 9
From Sunday, October 6 to Friday, October 11 from 10 p.m. to 5 a.m., the ramp from the Golden Glades Interchange to southbound SR 9 will be closed and traffic will be detoured as follows:- Take the ramp to southbound SR 9A/I-95
- Exit at SR 916/Opa-locka Boulevard and turn right onto westbound SR 916/Opa-locka Boulevard
- Turn right onto northbound NW 22 Avenue or continue west and turn right onto northbound NW 27 Avenue to access SR 9
- Ramp Closure: SR 9 to the Golden Glades Interchange
On Wednesday, October 9 from 10 p.m. to 5 a.m., the ramp from northbound SR 9 to the Golden Glades Interchange will be closed and traffic will be detoured as follows:- Go east on Opa-locka Boulevard
- Take the ramp onto northbound I-95
NW 151 Street
- Full Closure: NW 151 Street between SR 7/US 441/NW 7 Avenue and I-95
From Friday, October 4 at 10 p.m. around the clock until Monday, October 7 at 5 a.m. and Monday, October 7 to Friday, October 11 between 10 p.m. and 5 a.m., NW 151 Street will be closed in both directions.
- All lanes along eastbound NW 151 Street will be closed nightly between SR 7/US 441/NW 7 Avenue and I-95 and traffic will be detoured as follows:
- Go south on SR 7/US 441/NW 7 Avenue
- Turn left onto eastbound SR 916/NW 135 Street
- Turn left onto northbound NW 5 Avenue
- Turn right onto eastbound NW 151 Street
- All lanes along westbound NW 151 Street will be closed nightly between SR 7/US 441/NW 7 Avenue and I-95 and traffic will be detoured as follows:
- Go south on NW 5 Avenue
- Turn right onto westbound SR 916/NW 135 Street
- Turn right onto northbound SR 7/US 441/NW 7 Avenue
- Turn left onto westbound NW 151 Street
NW 6 Avenue
- Around-the-clock Full Closure: NW 6 Avenue between NW 151 Street and NW 162 Street
Drivers and pedestrians who want to go north onto NW 6 Avenue from the intersection of NW 151 Street and NW 6 Avenue will be detoured as follows:- Go east along NW 151 Street
- Turn right onto southbound South Biscayne River Drive
- Take the third exit at the roundabout onto northbound North Miami Avenue
- Turn left onto northbound Memorial Highway, which converts to NW 2 Avenue
- Continue north along NW 2 Avenue to NW 165 Street
- Drivers and pedestrians who want to go south onto NW 6 Avenue from the intersection of NW 165 Street and NW 2 Avenue will be detoured as follows:
- Continue south along NW 2 Avenue, which converts to Memorial Highway
- Turn right onto southbound North Miami Avenue
- Turn right onto northbound South Biscayne River Drive
- Turn left onto westbound NW 151 Street
- Continue west along NW 151 Street to NW 6 Avenue
Project Progress
On October 1, construction crews began installing the GGI Project’s first bridge beams. The photos below show the beams for the new ramp that will connect the Palmetto Expressway and Florida’s Turnpike to/from the intersection of NW 167 Street and NW 2 Avenue.