Important: Northbound I-95 Exit Ramp to NW 2 Ave is Now at Exit 12B

Week of March 29, 2026

Project Closures

Map-closure-March-27-2026
  • lane closure icon

    Lane Closure

  • local traffic only icon

    Detour

  • new traffic pattern icon

    New Traffic Pattern

Check Live Map

The following closures are scheduled between Sunday, March 29 and Friday, April 3. These closures will allow crews to perform bridge work, roadway paving, drainage work and temporary concrete barrier wall installation.

🌐 Check out all the project details at www.Go-GGI.com.

👉 Follow our social media page on 𝕏 @GoGGI_FDOT for the latest updates.

I-95

  • Ramp Closure: northbound I-95 to westbound S.R. 826/Palmetto Expressway
    From Monday, March 30 to Friday, April 3 between 10 p.m. and 5 a.m., the ramp from northbound I-95 to westbound S.R. 826/Palmetto Expressway will be closed and traffic will be detoured as follows:
    • Continue north along I-95 and take the ramp to S.R. 7/U.S. 441/NW 2 Avenue
    • Turn left onto westbound NW 7 Avenue Extension
    • Continue west for westbound S.R. 826/Palmetto Expressway
  • Closure: northbound I-95 Express Lanes
    From Monday, March 30 to Friday, April 3 between 10 p.m. and 5 a.m., drivers who want to take the northbound I-95 Express Lanes between NW 30 Street and S.R. 860/NE 183 Street/Miami Gardens Drive will be detoured to use the general purpose lanes along I-95.
  • Around-the-clock Ramp Closure: northbound I-95 exit to NW 151 Street
    The exit ramp from northbound I-95 onto NW 151 Street (Exit 11) remains closed through summer 2026. Traffic is directed to use the next exit ramp onto eastbound S.R. 826/NW 167 Street (Exit 12B) or also the previous exit onto S.R. 916/NW 135 Street (Exit 10B).

  • Lane Closures: I-95 between NW 135 Street and the Golden Glades Interchange
    • At 9 p.m., one lane in both directions will be closed nightly as needed
    • At 11 p.m., a second lane in both directions will be closed nightly as needed
    • All lanes will reopen at 5 a.m.

Florida’s Turnpike

  • Full Closure: southbound Florida’s Turnpike between S.R. 852/NW 215 Street/County Line Road and the Golden Glades Interchange
    On Thursday, April 2 between 10 p.m. and 5 a.m., all lanes along southbound Florida’s Turnpike will be closed at S.R. 852/NW 215 Street/County Line Road and traffic will be detoured as follows:
    • Take Exit 47 to S.R. 817/NW 27 Avenue
    • Turn right onto southbound S.R. 817/NW 27 Avenue
    • Turn left for the ramp onto eastbound S.R. 826/Palmetto Expressway and continue east to the Golden Glades Interchange
  • Ramp Closure: southbound Florida’s Turnpike to NW 167 Street
    On Monday, March 30 between 10 p.m. and 5 a.m., the ramp from southbound Florida’s Turnpike to NW 167 Street will be closed, and traffic will be detoured as follows:
    • Take the ramp to southbound I-95
    • Exit at S.R. 7/U.S. 441/NW 7 Avenue
    • Turn right onto northbound S.R. 7/U.S. 441/NW 7 Avenue
    • Take the ramp to S.R. 826 Beaches for NW 167 Street
  • Ramp Closure: southbound Florida’s Turnpike to southbound I-95
    On Wednesday, April 1 between 10 p.m. and 5 a.m., the ramp from southbound Turnpike to southbound I-95 will be closed, and traffic will be detoured as follows:
    • Take the ramp to eastbound S.R. 826 Beaches/NW 167 Street
    • Turn right onto southbound NE 6 Avenue
    • Turn right onto westbound S.R. 916/Opa-locka Boulevard
    • Take the ramp for southbound I-95
  • Lane Closures: Florida’s Turnpike between S.R. 860/NW 183 Street/Miami Gardens Drive and I-95
    • From 9 p.m. to 5 a.m., up to two lanes in both directions will be closed nightly as needed

S.R. 826/Palmetto Expressway

  • Ramp Closure: eastbound S.R. 826/Palmetto Expressway to southbound I-95
    On Wednesday, April 1 between 10 p.m. and 5 a.m., the ramp from eastbound S.R. 826/Palmetto Expressway to southbound I-95 will be closed, and traffic will be detoured as follows:
    • Continue east on S.R. 826/Palmetto Expressway to NW 7 Avenue Extension
    • Turn right onto S.R. 7/U.S. 441/NW 2 Avenue
    • Take the ramp for southbound I-95
  • Lane Closures: S.R. 826/Palmetto Expressway between NW 12 Avenue and NW 7 Avenue Extension
    • At 9 p.m., one lane in both directions will be closed nightly as needed
    • At 11 p.m., a second lane in both directions will be closed nightly as needed
    • All lanes will reopen at 5 a.m.

S.R. 7/U.S. 441/NW 7 Avenue

  • Ramp Closure: northbound S.R. 7/U.S. 441/NW 7 Avenue to northbound I-95
    On Wednesday, April 1 and Thursday, April 2 between 10 p.m. and 5 a.m., the ramp from northbound S.R. 7/U.S. 441/NW 7 Avenue to northbound I-95 will be closed and traffic will be detoured as follows:
    • Take the ramp to eastbound S.R. 826 Beaches/NW 167 Street
    • Turn left onto northbound S.R. 915/NE 6 Avenue
    • Turn right onto eastbound S.R. 860/NE 183 Street/Miami Gardens Drive
    • Take the ramp onto northbound I-95
  • Ramp Closure: Golden Glades Interchange to S.R. 7/U.S. 441/NW 7 Avenue
    On Tuesday, March 31 between 10 p.m. and 5 a.m., the ramp from the Golden Glades Interchange to southbound S.R. 7/U.S. 441/NW 7 Avenue will be closed and traffic will be detoured as follows:
    • Take the ramp to southbound I-95
    • Exit at S.R. 916/Opa-locka Boulevard and turn right onto westbound S.R. 916/Opa-locka Boulevard
    • Turn left onto southbound S.R. 7/U.S. 441/NW 7 Avenue

S.R. 9

  • Ramp Closure: Golden Glades Interchange to S.R. 9
    On Tuesday, March 31 between 10 p.m. and 5 a.m., the ramp from the Golden Glades Interchange to southbound S.R. 9 will be closed and traffic will be detoured as follows:
    • Take the ramp to southbound I-95
    • Exit at S.R. 916/Opa-locka Boulevard and turn right onto westbound S.R. 916/Opa-locka Boulevard
    • Turn right onto northbound NW 22 Avenue or continue west and turn right onto northbound NW 27 Avenue to access S.R. 9

NW 167 Street

  • Ramp Closure: eastbound NW 167 Street to southbound I-95
    On Wednesday, April 1 between 10 p.m. and 5 a.m., the ramp from eastbound NW 167 Street to southbound I-95 will be closed and traffic will be detoured as follows:
    • Enter eastbound S.R. 826/Palmetto Expressway at NW 17 Avenue
    • Continue east to NW 7 Avenue Extension
    • Turn right onto S.R. 7/U.S. 441/NW 2 Avenue
    • Take the ramp for southbound I-95

S.R. 112/Airport Expressway

  • Lane Closures: S.R. 112/Airport Expressway between NW 22 Avenue and I-95
    • At 10 p.m., one lane in both directions will be closed nightly as needed
    • At 11 p.m., a second lane in both directions will be closed nightly as needed
    • All lanes will reopen at 5 a.m.

NW 171 Terrace

  • Around-the-clock Full Closure: NW 171 Terrace
    NW 171 Terrace between NW 2 Court and NW 2 Avenue remains closed around the clock through early 2027 for overhead bridge work. Traffic is being detoured to NW 7 Avenue Extension.

NW 6 Avenue

  • Around-the-clock Full Closure: NW 6 Avenue between NW 151 Street and NW 162 Street
    Drivers and pedestrians who want to go north onto NW 6 Avenue from the intersection of NW 151 Street and NW 6 Avenue will be detoured as follows:
    • Go east along NW 151 Street
    • Turn right onto southbound South Biscayne River Drive
    • Take the third exit at the roundabout onto northbound North Miami Avenue
    • Turn left onto northbound Memorial Highway, which converts to NW 2 Avenue
    • Continue north along NW 2 Avenue to NW 165 Street
  • Drivers and pedestrians who want to go south onto NW 6 Avenue from the intersection of NW 165 Street and NW 2 Avenue will be detoured as follows:
    • Continue south along NW 2 Avenue, which converts to Memorial Highway
    • Turn right onto southbound North Miami Avenue
    • Turn right onto northbound South Biscayne River Drive
    • Turn left onto westbound NW 151 Street
    • Continue west along NW 151 Street to NW 6 Avenue

Project Progress

Below is a photograph facing west of the recently installed bridge beams to widen the northbound Turnpike Connector ramp, which connects northbound I-95 to westbound S.R. 826/Palmetto Expressway and northbound Florida’s Turnpike.

Photograph facing west of the recently installed bridge beams for the widened northbound Turnpike Connector ramp, which connects northbound I-95 to westbound S.R. 826/Palmetto Expressway and northbound Florida’s Turnpike (March 2026).

Join Us in the Community

Wednesday, April 1
11 a.m. to 1 p.m.
Wawa
590 NE 167 Street
Miami, FL 33162

Friday, April 3
11 a.m. to 1 p.m.
Walmart
1425 NE 163 Street
North Miami Beach, FL 33162

Meet team members and learn the latest about the GGI Project, including upcoming work and lane closures. Ask questions and stay in the know.

Senior Community Outreach Specialist Sergies with a Jackson North Medical Center worker, who passed by to ask questions at the NW 183 Street Presidente Supermarket on February 25, 2026.