From Friday, April 17 at 9 p.m. through Monday, April 20 at 5 a.m., construction activities will require continuous lane closures along southbound I-95 at NW 135 Street to perform concrete pavement work. The closures are scheduled as follows:

Friday, April 17 at 9 p.m. through Monday, April 20 at 5 a.m.

  • Both southbound I-95 Express lanes will be closed.

Friday, April 17 at 10 p.m. through Saturday, April 18 at 10 a.m.

  • Three southbound I-95 general purpose lanes will be closed.
  • One southbound I-95 general purpose lane will remain open.
  • The entrance ramp from NW 151 Street to southbound I-95 will be closed.
    • Traffic will be directed to use the entrance ramp at NW 135 Street.

Saturday, April 18 at 10 a.m. through Monday, April 20 at 5 a.m.

  • Two southbound I-95 general purpose lanes will be closed.
  • Two southbound I-95 general purposes lanes will remain open.

This concrete pavement work is part of the ongoing improvements to relocate the southbound I-95 Express toll gantry from NW 144 Street to NW 135 Street.